Sunday, July 19, 2009

pick up

here is what has been happening over the last two weeks; all windows and doors have been installed, all interior lights and electrical boxes have been hung, and all gas, water, and sewer lines have been plumbed. minor items [exterior lights for deck, strapping of plumbing lines, coil straps installed on walls] need to be taken care of before we get inspections on rough electrical and plumbing, as well as rough framing for an approval to wrap and insulate the house.